<aside>
🚆
Start here. PI Command Center is the system of record for your Agile Release Train between PI planning events: WSJF prioritization, PI objectives and predictability, ROAM risks, cross-team dependencies, and Inspect & Adapt, all connected.
</aside>
How it works
- Prioritize: score features in the WSJF Feature Backlog. The highest WSJF goes into the next PI.
- Plan: teams set PI Objectives, marked committed or uncommitted, and business owners assign planned business value.
- Connect: cross-team dependencies are logged with the iteration they're needed by, the digital version of the program board's red strings.
- Manage risk: program risks are ROAM'd (Resolved, Owned, Accepted, Mitigated) and linked to features.
- Measure: at the end of the PI, business owners score actual value. The PI Predictability Measure calculates automatically.
- Improve: run Inspect & Adapt using the built-in workshop guide.
Program Increments
WSJF Feature Backlog
PI Objectives
ROAM Risk Board
Dependencies
🎯 ART Dashboard
Risks that still need attention (Unroamed or Owned):
Untitled
Dependencies that are at risk or blocked:
Untitled